Pyrum Reactor 2 ramped up to target temperature under production conditions for the first time
Pyrum Innovations AG has announced the first successful warm-up of the new reactor 2 at its main plant in Dillingen/Saar. The reactor was started up and heated to the production temperature of around 650 °C for the first time. It was fed with granulate, and the dosing system was successfully tested so that the first pyrolysis oil could be produced in small quantities.
Pascal Klein, CEO of Pyrum Innovations AG stated; “In the course of the warm commissioning that started at the end of Octo...